Project Showcase
2010 Sidewalk Enhancement Project
Agency: | Clark County |
---|---|
Status: | Completed |
FHWA Aid#: | 2006(059) |
Project Type: | Pedestrian & Bicycle Facilities |
Description: | Construct concrete curb and sidewalk along 94th St., NW 1st Av., and 72nd Av. |
Termini: | Various |
Project Length: | 0.12 miles |
Completed: | May 22, 2013 |
Federal Funds | Project Cost | Schedule | Obligation | |
---|---|---|---|---|
Preliminary Engineering | $45,000 | $45,000 | July 15, 2009 | August 12, 2010 |
Right of Way | $15,000 | July 15, 2009 | January 1, 2010 | |
Construction | $245,000 | $245,000 | November 1, 2010 | September 1, 2011 |
Total | $290,000 | $305,000 |
Project Photos
List of all projects.