Southwest Washington Regional Transportation Council

Project Showcase

Jefferson Realignment Project

Agency: Vancouver
Status: Under Construction
FHWA Aid#: 4255(001)
Project Type: Reconstruction: No Added Capacity
Description: Realign intersections at 13th Street to create a single intersection. Reconstruct road to current standards, and continue Waterfront Multi-use trail to Mill Plain Blvd.
Termini: W Evergreen Blvd to Mill Plain Blvd
Project Length: 0.46 miles
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $975,000 January 15, 2017 January 15, 2017
Right of Way $1,850,000 January 15, 2020 July 12, 2023
Construction $5,040,000 $11,675,000 September 15, 2024 September 6, 2024
Total $5,040,000 $14,500,000    